What exactly is the community delayed the intersection?
Author:Huizhou TV Station Time:2022.08.01
Recently, Mr. Ling, Huicheng District, reported to the media that he bought a commercial house in Donghuaxuan Community in the city in the city. According to the contract, it will be closed on December 31 last year, but the developer will be again three again and again. The land was lost to the owner and could not close the building until now. And developers are also unwilling to negotiate with the owner for default compensation.
There are two AB buildings in Donghuaxuan Community, about 160 households. Mr. Ling purchased a 90 -square -meter commercial house in November 2021, which agreed to pay the building on December 31, 2021. However, on the date of delivery, the developer was lost. Since the beginning of this year, the developer Huizhou He Run Trading Co., Ltd. has promised the owner to submit the building next month again and again. As a result, the owner will be happy again and again.
Mr. Ling, owner of Donghuaxuan Community: Until June 30 this year, the so -called developer representatives actually told us that the property was simply told to us. You can hand over the building, and finally did not deliver the building until the end of June. When we gathered here, they had a written commitment to deliver the building on July 30, but so far, the developer has not responded.
On July 1, the developer issued an apology letter to the owner, saying that due to the epidemic and policy adjustment, the building could not be delivered on time. At present, the main project of the house has been completed, and the installation of indoor and outdoor decoration projects has been completed. It is expected that the relevant departments will come to the joint acceptance on July 5th, and the owner will be notified to close the building on July 31.
Mr. Ling introduced that he called the Huicheng District Housing and Construction Department on July 25, and the staff responded that he did not receive the information uploaded by Donghua Xuan District.
Mr. Ling, owner of Donghuaxuan Community: The quality inspection is over, but the information for the filing of the completion has not been submitted, and then the developer never appears and responds to us.
Mr. Ling said that the owners are currently worried that the community will be rotten, and the developers are reluctant to negotiate with the owner for default compensation. The reporter found Mr. Zhang, a staff member of the community developer. He said that the acceptance of real estate this year is different from previous years, and the joint acceptance of joint acceptance has been added, so it has repeatedly delayed the time of delivery.
Mr. Zhang, a staff member of Donghua Xuanlou Community: The first reason is the impact of the epidemic; the second reason is that a joint acceptance was added in 2022. Our staff has not experienced this After the information was submitted to the window, I thought it had been completed. In fact, I had to upload this information on the background website. We are also deeply sorry for the extension of the extension of the property, and at the same time we will actively coordinate with the owner. It is expected that it is no problem to deliver the building in August. I hope the owners will understand our difficulties.
- END -
Shanghai Disneyland resumed operation on June 30
/On June 28, the Shanghai Disney Resort announced that Shanghai Disneyland will r...
The most complete "dry goods" guide!The latest entry and exit policy 10 questions!
As the domestic epidemic has entered a normal state, the willingness of citizens i...