Less than two years!All cap

Author:Hefei Daily Time:2022.07.31

July 31,

As the last side of the top plate is poured, it is completed,

Line 2 Dongyan Line Yaigang Road Station

The main structure is smoothly capped,

The stations capped on the 11th main structure across the line.

So far,

East extension of Rail Transit Line 2 in our city

The main structure of the 11 -seat station has all been capped,

For the third phase of the rail transit

The first line to realize the main structure of the station.

Yaogang Road Station is located at the intersection of Yaogang Road and the planning of the Sirot Mountain Road. It is arranged north and south of the planning of the four -pillar, three -span steel concrete box structure station. The number line is the second floor station, and the transfer part is the third floor.

The total length of the station is 281 meters, and the amount of earthquakes in the foundation pit is about 114,200 cubic meters. The main structure of the station is divided into 12 construction sections, with a total of 37 structural sections, and the total concrete is about 39,000 cubic meters.

Bring you a time shaft

Sort out the progress of the east extension of Line 2

Extended reading

Since the construction of the third phase of the project on September 29, 2020, the Hefei Rail Group has led the participating units to work hard and to promote the construction progress. Among them, the east extension of Line 2 is the first batch of three -phase project projects, and the construction of various projects is the first.

Complete traffic guidance reform and enclosure in 7 days

Completed the construction of the first site surrounding pile construction in 37 days

At 84 days, the first station main body earth excavation

Complete the first station main body of the soil excavation of the first station in 171 days

Completed the first shield machine to the well 233 days

Complete the first station cap at 241 days

Complete the starting of the first shield machine at 254 days

Complete the first interval through 323 days

Complete the first interval dual -line through 353 days

After 670 days, the main structure of the station was capped ...

up to now,

A total of 72 stations in the third phase of the project

There are already 38 main structures to be capped,

A total of 141 shields single -line interval

There are already 34 stamps and 51 articles are being excavated.

There have been 4 in the five elevated range.


Wen Tu, Video | All Media Reporter Wang Junchao

Editing and Editing | All Media Editor Dong Yuankang

Produced | "Lakeside Point" Rong Media Studio, "Shanshan is not late" Rong Media Studio

- END -

Xinyang City Audit Bureau: Pay attention to the natural gas price adjustment mechanism to optimize the operating environment of gas companies

In June 2022, the Audit Bureau of Xinyang City, Henan Province, in the audit surve...

Welcome to the 20th National Congress of Drugs in Action-Jinyu Street, Longhua District, Haikou to carry out banned drug preaching into bank school activities

In order to continuously deepen the education of adolescent drugs, further strengt...