Jinan Tourism Road East Yan Project Qinglongshan Tunnel Shuangdou through the entire line

Author:Qilu Yiyi Time:2022.06.16

Reporter Yu Bosheng

Following the right line of the Laoshan Tunnel on June 12, on June 15, the right line of the Qinglongshan Tunnel of the Jinan Tourism Road East Extension Project went through smoothly. At this point, the left and right double lines of the Qinglongshan Tunnel have been fully connected, marking that the project construction has made breakthrough progress again.

At 16:28 pm on June 15th, with a sound of artillery, the right line of Qinglongshan Tunnel achieved penetration, marking that the two -line Qinglongshan Tunnel's two -line Qinglongshan Tunnel of the Tourism Road has all penetrated. On the same day, the main structure of the left line of the Qinglongshan Tunnel was successfully completed, and the manpower and material resources on both sides of the tunnel were more unobstructed, and it was no longer blocked by the mountain.

According to reports, the construction of the Qinglongshan Tunnel has gone through a series of problems such as temporary land tensions, blasting procedures restrictions and surrounding impacts. With the deployment of the development center of Jinan City and the help of the local headquarters, the east extension project of the tourist road is refined and deployed Project construction tasks; integrate resources, promote the implementation of projects, and advance the project construction step by step.

The Dongyan project of the tourist road spans the east of Licheng, High -tech, and Zhangqiu. After the Zhangqiu District South Outer Ring, the project will further improve the traffic environment in the eastern urban area, divert through the ten roads, and open the entire urban traffic network. It will play an important role. At the same time, it will be further closer to the distance from Laiwu and Steel City, connect with Jiwei high speed, and become another fast channel connecting Jinan, Weifang and Jiaodong Peninsula, which is important for serving the strategy of serving the strategy of the provincial capital of the provincial capital in the new era. significance.

Up to now, the lower part of the lower part of the West Juye Bridge of the East Extension of the Jinan Tourism Road has basically been completed; the Laoshan Tunnel is about to be opened throughout the line;

- END -

Jining High -tech Zone Jixizhuang Street carried out special propaganda activities for rectification of elderly fraud

Recently, in combination with the special attacking operation of the new crown vac...

The Lanshan District Taxation Bureau has carried out in -depth \"learning enlightenment and in

Since mid -April, the Lantashan District Taxation Bureau has launched a public co...