CRRC Songyuan New Energy Equipment Industrial Park: Ten billion projects completed in 200 days

Author:Jilin Daily Time:2022.07.29

Recently, the reporter walked into Zhongxian Songyuan New Energy Equipment Industrial Park. The general commander of the construction site said that the project started construction on February 28. As of now, 98,000 square meters of plant construction has been completed. After the project is completed, it is a major transformation for CRRC.

From November 17th to February 28th, 2021, within 100 days, it overcomes unfavorable factors such as ice, cold, snow, and freezing, strive for time, fight day and night, and lay a solid foundation for the project to fully start the project. Complete facilities such as electricity, drainage, network, heating pipe network and other facilities; complete land flat, foundation digging, boundary repair, pile foundation test, land delisting, industrial and commercial registration, information filing, and the processing of construction requirements.

Tan Weiqi/Photo

During the Spring Festival, the cadres and employees and construction teams of the Yadahong Industrial Concentration Zone gave up the rest time. The machinery and equipment kept working. "".

On February 28th, the full launching ceremony of the concentrated start of the province's spring project and the full launching ceremony of CRRC Songyuan New Energy Industry Base Project was held, marking the press key of CRRC Songyuan New Energy Industry Base Project, and entered the gold construction period at full speed.

After the unremitting efforts of the project special class and all construction staff, the 3087 pile foundation of the total installation, motor, and logistics plant area was completed in March, with a completion rate of more than 90%. The construction of civil construction has laid a solid foundation.

Facing the severe epidemic situation in the province, while doing a good job of prevention and control, the project construction has steadily advanced. On July 11, the entire line of products was offline, and the office building and dormitory building planned to be put into use before October 31.

It is reported that after the production of the industrial park has been produced on July 11, the production of four whole machine has been completed. At present, there are 120 orders in their hands, and all orders are expected to complete all orders at the end of November. (Tan Weiqi)

Source: Zhongxin.com Jilin

- END -

Jiujiang continued to rectify uncivilized dogs, these behaviors were exposed

Jiujiang News Network (Jiujiang Daily All Media Reporter Zhang Qian) In order to further regulate the citizens' citizens' citizens' civilized behavior, from March to the end of September, the Municipa...

A number of new stations and new lines open a new picture of the national railway "upper"

Xinhua News Agency, Beijing, June 20th.Xinhua News Agency reporters Fan Xi and Hou...