Kaijiang, Sichuan: The resettlement room has been repaired for ten years and has not been delivered to the end of 20 million projects, but "dragged" nearly 50 million yuan overdue costs

Author:Cover news Time:2022.07.28

Dazhou City 24th issue of "Sunshine Ask Into" show scene scene

Cover Journalist Zengye Photography Report

It can issue a resettlement fee of nearly 50 million yuan, but it cannot get an engineering end of 20 million yuan. After ten years of resettlement houses in Pu'an Town, Caijiang, Sichuan, the house has not been delivered for ten years. More than 700 households have a lot of opinions. The government has to pay them 1.2 million yuan per month. As of the first quarter of 2022, a total of 49.824 million yuan has been paid. At the same time, the government's debate of the 20 million yuan project of the construction party was not allocated.

On July 28, the "Sunshine Ask" program in Dazhou City, Sichuan Province was broadcast, and exposed the problems existing in the construction of Kaijiang County in the "28 Picking Point". This issue focuses on the construction of major projects, and has also exposed the construction progress of Wanyuan City with the demonstration project of the Workers' Generation -Weijia Town and the key project of the Dazhou Municipal Government -the key project of the PetroChina 7101 oil depot. question.

The "ten -year pain" of demolition households

Someone waited until his death and could not live in a new house

Kaijiang County Payment Transition Resettlement Fee credentials

"When the resettlement house started, my son was not married yet. Now the grandson is 1 meter high, and the house has not been paid yet." "After the house was relocated, the house was rented and moving around. Can realize this desire. "In the unannounced visits on the show on the show, the demolition households who" Twenty -eight Picking Points "in Kaijiang County mentioned that the resettlement houses that had not been delivered for ten years, so they would not hit a place without a place. Come.

On the other side, after seeing an unannounced visitor group, the resettlement room construction party also suffered bitter water. "This project has made me lose money. I sold my house and the car was sold ..." The person in charge of the construction party said that the project was a key project of the county government. The problem of being arrears by the government had to advance capital. Over time, there are more and more problems left over from history, and the construction party has also fallen into the dilemma of lack of funds.

As of the broadcast, the government still owes about 20 million yuan in project funds. More than 700 households who did not live in the house were repeatedly asked for the government to discuss the law. Data from the Natural Resources Bureau of Kaijiang County show that from 2014 to the first quarter of 2022, Kaijiang County Finance has paid a total of 49824394.24 yuan.

In the past ten years, as one of the competent departments, the "first leader" of the Kaijiang County Housing and Construction Bureau has been changed twice. In order to clarify the ins and outs, the current director and the first two directors were "requested" to the scene to be questioned by the show team. where is the problem? Where is the blocking point? Is there a situation of inaction and chaos? How to solve it next? At the scene of the show, the relevant responsible persons and county leaders who were asked Lian said that they were sincere accepting criticism, the questions were fully received, and a rectification commitment was made on the spot, and rectification measures and methods were put forward.

Provincial Development and Reform Commission twice sent a letter

The problem of slow demonstration projects still exists

The Sichuan Provincial Development and Reform Commission sent a letter to the Dazhou Development and Reform Commission twice

Wanyuan City Huangzhong Town Ranjiaba Bridge, with a total width of 8 meters and a total length of 120 meters, with a total investment of 6.35 million yuan. Among them, the central budget invests 4.9 million yuan and local investment is 1.45 million yuan. Wanyuan City took the order of "1020] No. 59" to the project competent department of the project authority and the project owner. In addition to the actual construction content, in addition The total width of the bridge deck is 11 meters wide and 108.5 meters long). It is also necessary to build a newly built road with a length of 302.8 meters and a width of 7 meters. The total investment is 11.5 million yuan.

This bridge is a people's livelihood project that benefits the people and the people, but the progress of the project construction is slow. The unannounced visits team found that only two or three workers were constructed at the construction site. In this regard, the construction party explained that the main reason for the slow progress was the lack of money, "because the government's funding was not timely."

Is the facts as the construction party said? In October and January 2022, the Sichuan Provincial Development and Reform Commission sent a letter twice to the Dazhou Development and Reform Commission to remind the project with the problem of construction progress and lagging funds. Project construction progress to ensure the quality of the project. However, the construction progress of the project is still slow, and the scene of the unannounced visitor group saw at the construction site.

The unannounced investigation found that the project's control price was 6.9725 million yuan, and the project was implemented through public bidding, and the winning price was 6.798139 million yuan. The project's funds were in place in October 2020, and the project was officially started in May 2021. Since the project funds have already been in place, why not use the project? Lian Fa found on the spot that the progress of the project was lagging behind, and the relevant departments were slow as the situation, resulting in the failure to allocate the relevant funds in time.

Tang Chao, a lawyer among the members of the Lian Lian delegation, pointed out that according to the relevant provisions of my country's "Administrative Measures for the Special Funding of the Workers", the traffic, development and reform, and the financial department shall timely allocate funds in accordance with the procedures. Check it. Otherwise, it will bear the corresponding legal consequences. Asked the object of Lian, he stated on the spot, immediately rectified related issues, held accountability of relevant responsible persons, and at the same time, he would check similar problems.

Some netizens comment

Standing Committee of the Municipal Party Committee on -site reviews

Requires further implementation of project promotion responsibilities

At the scene of the show, a delegation consisting of expert representatives, legal workers, and CPPCC members conducted on -site analysis and comments around the case.After the integration of the integrity, the Inquiry and Commentation Troupe and the Media Observation Troupe consist of "two representatives and one member", the masses, and the invited supervisors were composed of the interviews and supervisors.Tang Tingjiao, member of the Standing Committee of the Dazhou Municipal Party Committee and Secretary of the Party Working Committee of the Economic Development Zone Economic Development Zone of Dazhou, attended the live broadcast activities and made a review, requiring party committees and governments at all levels to pay more attention to the work of all aspects of the project construction, further implement the responsibilities in the process of promotion of the project, and form the entire city.The upsurge of grasping projects and grabbing projects, with the actual results of project construction, to promote the high -quality development of Dazhou, to promote the establishment of the strategic fulcrum in the northern wing of the Shuangcheng Economic Circle in Chengdu -Chongqing area, and welcome the 20th National Congress of the Party with excellent results.Victory was held.

[If you have news clues, please report to us.Report WeChat Follow: IHXDSB, Report QQ: 3386405712]

- END -

When the summer is coming, you must learn to avoid your mouth, eat less "3", eat more "3 grass", and pass the sky safely

No matter which step people go, they have to find some fun and think about it. Yes...

Careful passengers take the high -speed rail to forget the computer package Linyi Qufu's love relay belongs to the original Lord

On June 14th, Thank you for your enthusiastic service, if you were not for helping...