Xiongshang Hezong Zedong Route Bridge continuous beam
Author:Heze Daily Time:2022.06.16
The Bridge of the Xiong Business Hezong Zedong Route Bridge is the main bridge connecting He Zedong Station and EMU for trains on the high -speed rail line from Hezong Station to the EMU for maintenance. On June 15th, the reporter came to the construction site of the Bridge of the Zedong Zedong Route in Hezhang to learn about its construction.
Because it is closer to Hezong Zedong Station and high -speed rail routes, the Bridge of the Hezong Zedong Zedong Motor Walk needs to cross the road, river channels, etc. At the construction site on the bank of the river, the bridge pier body of the "hanging basket" has been installed in a T -shaped body. Workers may be constructed above the continuous beam, or climb up through the construction stairs; below the huge bridge, the cranes and construction materials are stored on the surrounding open space.
The current construction situation has no effect on the normal traffic of the highway. According to the meteorological forecast, the maximum temperature on June 15 was higher than the previous two days. At 11 o'clock, the workers successively climbed from the continuous beam to the ground through the blue construction stairs, and rushed to the rest area with the kettle.
According to Han Minghui, the technical director of the five -point department of the High -speed Railway Project Department of the China Railway Tenth Bureau: "The Box Bridge of the Box House of the Heroes of the Hezhery is more than 800 meters in length, which is a single -line bridge. At present, the main construction content is the upper structure construction, which is the box beam beam beam Prefabrication. At present, the Jianziliang has completed one span, and the continuous beam at the southernmost tip of the EMU has been completed. The 80 -meter continuous beam has been completed two blocks, and two simple beams are under construction. "
According to reports, the continuous beam mainly adopts the hanging basket construction process. This process can maximize the on -site terrain, such as 80 meters span across the Wanfu River to ensure that the construction process is more secure and reliable, and the construction of construction is smoothly promoted.
Han Minghui said: "At present, the difficulty of construction is mainly in summer construction. The hot weather is likely to cause a common problem with concrete construction. We use measures such as automatic spraying and maintenance and construction at night to ensure that the concrete can reach the prescribed hardness and ensure the quality of construction."
According to reports, according to the construction schedule, the construction of the beams of the Bridge of Hezong Zedong Route Bridge will strive to end before entering the winter construction period.
Heze Newspaper All Media Reporter Yun Hua
- END -
Sichuan Longchang: Carry out energy -saving and low -carbon publicity activities Volunteer service to build a beautiful home
In order to advocate green low -carbon production lifestyle, actively create a str...
Is there any unforgettable experience in the bus line you often sit in?| Lens Night Talk
Do you also like to take a bus?Compared with the closed space of the subway, the b...