Juzhi Garden accelerates the construction of Xuzhuang's second "entrepreneurial" presses the "acceleration key"

Author:Dragon Tiger Net Time:2022.07.23

Longhu.com (Correspondent Yu Chen Xiaoxiao reporter Wei Heng) Recently, at the rear of Xuzhuang Juhuiyuan, Nanjing, there was a construction site, and a slag transport vehicle lined up the team to wait to be unearthed, a busy scene. This is the major project of Nanjing, Xuzhuang Juzhi Garden, is in full swing to arrange local transportation. At present, the construction of Jizhi Garden's pile foundation has been completed.

It is understood that Juzhi Garden and the built Juhui Garden belong to the second phase of Xuzhuang. It is located on the north side of Xuanwu Avenue, between Jubaishan and Baili scenery belt. The Juzhi Garden project makes full use of the characteristics of Jubaoshan. The overall shape of the building is completely zero, showing the mountains and greening, creating an observation platform in appropriate places to realize the penetration of each other with the natural landscape. Innocent, the building group is also part of the landscape of urban landscapes, and a subtle balance between cities and nature.

Earlier this year, affected by the spillover of the epidemic in some areas, the progress of Jizhi Park was slightly lagging. In order to make up the lost progress, the on -site construction was also promoted by overtime and racing against time.

"In order to ensure the progress of ± 0 at the end of the year at the end of the year, we first analyzed the characteristics of the project, clarified the project's construction technology difficulties, and then formulated a targeted construction technology route to ensure quality and safety. Under the premise, coordinate the construction forces such as machinery and equipment, make relevant materials to enter the field plan in advance, and organize construction in accordance with the "partition parallel construction, highlighting key procedures, timely interspersed operations, and dynamic adjustment of traffic '." Xuzhuang Gaoxin Xinxin Chen Xiaoxiao, the person in charge of the planning and construction department of the District Management Committee, introduced: "The original planning period of the support project is two months. We will complete the support project on May 31 by increasing the measures of the material machine and continuous construction of the day and night. The construction period is one month earlier than the original plan. In order to accelerate the progress of the construction pile construction, we invested 12 rotary excavators, 12 car cranes, 12 excavators, and 4 unplugged machines during the peak period. Construction, engineering piles finally completed the construction on July 4 this year, 45 days earlier than the original planned construction period. "

According to reports, compared with Juli Park, the Jizhiyuan project is more complete. The project itself is planned to build a supporting business of 12,640 square meters, a 4892 square meter convention and exhibition venue, and 873 talent apartments in the northern southeast youth apartment project planning and construction With a 1,000 -square -meter nursery, Metro Line 14, which is reserved, will further increase the second -phase transportation facilities. In the future, it will work with the "vitality of vitality such as Jixinyuan, Juxinyuan, Juxin Garden, Juli Garden, Jubao Technology City, and the Southeast Youth Exchange Project under construction to build a composite business, office, conference, supporting, living, leisure and other functions. Community".

The construction of major projects is only the first step, and it is the key to attracting quality and efficiency. "This year is the" construction year "of Xuzhuang Gao New District, and it is also the" China Merchants Year 'in Xuzhuang Gao New District. We have 5 major municipal projects in hand, including 4 construction categories and 1 in the early stage. At the beginning of the listing, the principle of the promotion work must be determined. At present, we have provided a customized plan for companies that have more than dozens of intentions. '. "Jiang Zenghui, the China Merchants Department of the Xuzhuang Gaoxin District Management Committee.

The second phase of Xuzhuang covers an area of ​​350 acres and can build an area of ​​about 900,000 cubic meters. Among them, the total construction area of ​​the Jizhi Park project is about 205,000 square meters, of which the building area above the ground is 146,000 square meters. Six buildings are planned and constructed. Listed company headquarters settled in.

- END -

WTT Championship Budapest Station: Wang Manyu "Three Kills" Ito Mika in one week

On the evening of July 21, Beijing time, the WTT champion Budapest Station continu...

130,000 people watch!Shenzhen Longgang Live Belt Belt "Post"

In order to comprehensively implement the Central Economic Work Conference and the...