Project Construction Speed Year | This "Half -annual report", Changsha County's results are dazzling

Author:Changsha County Rong Media Cen Time:2022.07.22

The rapid transformation of Wanjiali Road has been completed in the north extension line (including the power tunnel) project, and the construction of bridge piles, Chengtai, pier pillars, cover beams, beam boards, and road drainage engineering construction.

Wanjiali Road Fast Transformation of the North Extension Line (including Power Tunnel) project construction site.

Sanyi Intelligent Connected Card Project, Land A No. 1 and No. 2 factories have been put into operation.

Lanti Technology Expansion Projects 1, 2, and 3 projects have been completed and put into use. The main project of the Lot 4 has been completed, and the land construction is completed.

... ...

The "progress bar" of major projects is constantly refreshing. This year, Changsha County and Changsha Economic Development Zone strived to implement the "strong provincial capital" strategy, taking the opportunity to carry out the "project construction speed -up year" action, give full play to the leading role of the project on investment growth, and for the high -quality leapfrog development of the county's economy and society in the whole county Gathering power increases.

Wanjiali Road Fast Transformation of the North Extension Line (including Power Tunnel) project construction site.

According to data provided by the County Development and Reform Bureau, from January to June this year, 110 new projects in counties and districts should start, and 107 were actually started, with an operating rate of 97.3%. From January to June, 268 major projects in the county and districts completed an investment of 34.805 billion yuan, and the investment completion rate was 66.6%. The annual investment of 12 provincial key projects was 18.77 billion yuan, and the investment was 11.76 billion yuan from January to June, and the investment completion rate was 62.6%. The construction of county projects has been accelerated to be accelerated, and the dazzling "transcripts" are surrendered.

High -quality development requires high -quality projects

At the site of the relocation project of the relocation project of Changsha Bingbing Gas Line Petroleum Conferry Station in Changsha Bingbing, more than 50 workers at the scene were performing their duties, and the construction pipeline installation, filling system debugging, and lightning protection device detection were completed. At present, the overall progress of the project has been completed by 90%. It is expected that it will be completed in the acceptance stage at the end of August, and it can be completed and put into operation in early November.

The project is located on the east side of Huangxing Avenue, Mingyue Village, Dongyue Village, Goukou, Changsha County, with a total investment of 175 million yuan and a total land area of ​​about 25.96 acres. The main construction content is the newly built liquefied petroleum gas (LPG) storage station, including new office buildings, dormitories, dormitories Building, auxiliary rooms, fire pools, tanks, irrigation rooms, compressed machine rooms and other building facilities. The storage area is designed with 3 200M 设计 and 1 100M³ full pressure storage tanks. The average daily filling volume of 3,000 bottles after commissioning, and the annual irrigation volume can reach 15,000 tons/year.

The relocation project of Changsha Bingbutu Gas Line Petroleum Confusion Station in Changsha Bing, Xiukou Town, and workers are installed in the tank area.

According to reports, the income of the project will reach 77 million yuan after production, creating more than 80 posts. At the same time, the energy consumption structure will be further adjusted, the proportion of clean energy in one energy, and effectively regulates the local bottle liquefied petroleum gas market, and facilitates the living gas of surrounding residents.

"Due to the long rainy season this year, the project is affected by more weather. Under the assistance guidance of the county development, reform, urban management, emergency and other departments and intersection towns, we fully prepare for the preparation, accurately grasp the key nodes, and work in parallel after starting. Cross -construction, while continuously increasing manpower, materials, and mechanical investment. There are more than 160 personnel construction at the peak period, and it is used for three days a day to speed up the project progress. " People Wang Jianjian said.

Summer is hot, and the summer is strong. The construction staff of each project site still adhered to the scene, sweating like rain, and accelerating the speed of the project. Located at the intersection of Filili Road and Dongchang Road, Changsha County Songya Lake Ecological New Town Talent Apartment Tushi Fang and the basic pit support projects on the spot have overcome high temperature and hot weather and are undergoing infrastructure and other infrastructure. The total investment of the project is estimated to be about 980 million yuan, the total land area is about 47.7 acres, and the total construction area is about 129,000 square meters, which mainly includes commercial and service apartments. At this stage, the bidding of the earth and stone and the foundation pit support project has been completed. At present, the preliminary construction of the project and preparations for construction entry are currently underway. It is expected that the main project construction bidding will be launched in mid -to -late August, and the current stage of project construction will be completed at the end of November.

High -quality projects require high -quality implementation

Since carrying out the "Speed ​​Passage of Project Construction", Changsha County has adhered to the "front -line work method", so that the situation can be mastered in front line, the work is implemented in front, and the problem is solved in the front line. Submit the papers to create an atmosphere of "leading, competing, and leading".

"It's not the night, the day and the sun." The county has established a scheduling mechanism for the project office overall planning, county leadership joint point to promote the help, the responsible units fully build, the project's full service service and the full service of the project housekeeper, and the scheduling mechanism of "notification of one Monday, a January one -time scheduling, and a season of evaluation". The project responsible unit implements the "one picture and three list" hanging map combat mode, clarifying the special class, one strategy, one strategy to grab time, progress, and efficiency.

The ecological apartment of Songya Lake Ecological New Town, Changsha County, and the foundation pit support project, workers are stirring cement and mulberry.

At the same time, the entire county shall formulate a list of assignments in accordance with the principle of "classification, classification, and block", and directly assign the deputy county magistrate to the deputy county magistrate according to the category of problem categories to clarify and resolve the time. According to the form of the "six lists", the problems of 268 major projects in the district and county are classified and summarized, and the issue number system is implemented. On -site office, timely solve the problem of card blocking points.

- END -

Choispy is a typical "disease from the mouth" infectious disease. The effective way to prevent is to cultivate good health habits

Jimu Journalist Li ManyingOn July 11, the Wuchang District Health and Health Burea...

"Dictionary Letters and Visits Work Regulations ⑤" What is the supervision system of letters and visits work?How to investigate responsibility?

Effective supervision is the necessary condition to ensure the implementation of r...