Ask the government in Shandong | Gao Tang County's individual rain and sewage flow project progress slowly county magistrate: fully speed up the construction progress
Author:Qilu.com Time:2022.07.21
Qilu.com · Lightning News July 21 News Tonight "Ask the Government Shandong" aired the 132th issue, asking about the city.
The 12th Party Congress of the Provincial Party Congress proposed to promote the rain and sewage flow pipeline network of urban construction areas. This is also an important part of the construction of the infrastructure "seven networks". The reporter visited Liaocheng in many places and found that the rain and diversion projects in multiple places are stepping up construction. However, there are people in Gaotang County reported that their rain and diversion projects are a bit slow.
In front of the Yuhua Garden Community of Gulou Road, Gaotang County, the road was gelated to the width of only about one car. Vehicles that drove in at the same time in both directions wanted to meet the car, and they could only choose to be in the turning point of the road passing. It is easy to block when missing the corner. It brings a lot of inconvenience to nearby residents.
The reporter noticed that the construction project is under construction, and the construction time on the signs is about 60 days. However, nearby residents said that since the construction of March 28, the actual project progress has exceeded this period.
In Gaotang County, there are many sections that are under construction of rain and diversion infrastructure. The merchants located on both sides of Fuyuan Road told reporters that the construction of Fuyuan Road has not progressed for many days.
Fuyuan Road merchants reported: "No one has worked for more than a month."
Residents also reflected that the situation where natural gas had been cut off during the construction process had affected their daily life.
Why have there so many problems with rain and diversion transformation? The reporter came to the Housing and Construction Department of Gaotang County.
The staff of the Gaotang County Municipal Engineering Quality Service Center told reporters: "There are many difficulties during the construction process. The underground pipe network is complicated. The previous projects and pipeline units have no drawings.
Regarding the problems reflected in the show, Zhang Baishun, mayor of Liaocheng City, said: "Rain and stains are diverted to the city's flood prevention and the protection of the water environment. This problem is both a problem of people's livelihood and a problem in development. This requires us to strengthen our overall planning. Coordination and scientific layout must have sufficient funding for one aspect, and the other must solve the problem of slow progress. On the other hand, we must scientifically construct and optimize the construction plan. In the next step, we will send a working group. More importantly, work guidance to help the county level optimize the plan, and effectively solve the problem of rainfall diversion. "
Regarding how to promote the diversion of rain and stains in the next step, Yang Shuguang, the head of Gaotang County, said: "For these two roads, we will make scientific research and judging the weather conditions, and to speed up the construction progress and strive to be completed by August."
Lightning reporter Wang Xiaoming Haoyu Wang Wenlu report