On the morning of July 20, the National Health and Health Commission announced that as of 24:00 on the 19th, there were more than 1,300 confirmed cases and asymptomatic infections in Gansu Province, of which nearly 80%were asymptomatic infected, and Lanzhou City became a high incidence area. At present, the province's epidemic prevention and control situation is severe and complicated. At the key stage of overcome difficulties, the square cabin hospital will play an important role. During the reconstruction of this square cabin hospital, there were two undergraduate alumni at the School of Civil Engineering and Mechanics of Lanzhou University. Hospital project chief engineer, 2015 alumni Zhao Ziwu.

Time has returned to July 11. This round of Lanzhou epidemic has a trend. From Wuhan to Shanghai, there are three bureaus of China Construction with rich experience in the construction of squares. Its Northwest Company Lanzhou Branch has received the task of rebuilding Lanzhou Fang Cabin Hospital. Lanzhou New District Greenland International Convention and Exhibition Center, just opened.

Zhao Ziwu at the construction site

In March and April this year, Xu Hongli and Zhao Ziwu, a pair of sisters and sisters, were transferred from the projects in Hohhot, Inner Mongolia and Xigu District, Lanzhou to Lanzhou New District. Among them, an important project involved in the Lanzhou Airport with a total investment of about 3 billion yuan After completion, it will further enhance the capacity of the province's aviation port epidemic prevention and control, and effectively improve the carrying capacity of the entry flight of Zhongchuan International Airport in Lanzhou.

On the morning of July 11, the project department of the Lanzhou New District of China Construction Third Bureau received the task of reconstruction of the squares hospital. The heart of the heroes, do their best. In the case of insufficient workers, about 80 managers above the third level were in person, quickly assembled more than 120 construction personnel, set up commando teams, and fought day and night. The team overcomes the difficulties of traffic control and supplies during the prevention and control of the epidemic, and the rapid assembly of various materials such as car cranes, transportation vehicles, etc., more than 5,000 partition boards, 26 folding box houses and ordinary box houses, more than 900 beds and hydropower installation lighting , Wash and drink water and other supporting facilities, all were transported within 10 hours.

In 4 years, Zhao Ziwu, the chief engineer of the project and the previous engineer of the Lanzhou Airport International Health Station, continued to be coaches. Xu Hongli, who has just worked as a graduation internship for graduates of the 2022 civil engineering major this year, is responsible for the transformation of the project organization and logistical support.

With a order, the construction staff signed up. Where to need people, Xu Hongli coordinated the employees of the new district project to ensure that sufficient hands were sent.

Construction Site

After the personnel organization is uniform, it will start on time at 10 o'clock in the evening. While Zhao Ziwu took the drawings and modified drawings with the design institute, determined the construction plan, explained the construction requirements of special parts such as nurse stations to the workers, and stared at the construction details of the workers. At the beginning, the construction schemes such as drainage, hydropower connection, and other construction schemes were difficult. Zhao Ziwu adjusted the position of some ditch according to the situation, and finally achieved 784 quarantine beds.

After completing the renovation, Lanzhou New District Greenland International Convention and Exhibition Center Hall 6

That night, that day, Zhao Ziwu kept walking around in Hall 6 of 6,000 square meters, constantly explaining the construction requirements to the workers, took 20,000 to 30,000 steps, only resting in the car for 2 or 3 Hours. It took a long time to stand, and the waist was particularly painful, and the legs were particularly painful. "This is also the normal state of our construction industry staff." Zhao Ziwu said. Xu Hongli also worked overtime, sent countless news in the WeChat work group, made countless calls to ensure that the hands of the construction venues everywhere, and give everyone full logistics support.

In 5 hours, 784 beds were assembled; 8 hours, 26 functional rooms were lifted and modified. At 18:00 on July 12, it lasted 20 hours. The emergency battle of "no time to complete the task" was completed.

Xu Hongli at work

Because of the lack of manpower, in order to allow the square cabin hospital to put it into use as soon as possible, Xu Hongli also took colleagues to organize beds and prepare for necessities.On July 15th, the Lanzhou New District Greenland International Convention and Exhibition Center Fang Cabin Hospital was officially launched. As of July 17, 69 patients with unyielding infections had been received to implement isolation medicine observation.More beds.Sure enough, on the evening of July 19, Hall 5 was completed!It's night, Zhao Ziwu wrote in the circle of friends: "White+black ~ 5+6 Lanzhou, come on!"

Content source | Propaganda Department of the Party Committee of Lanzhou University (Rong Media Center)

Text | Faisa

Picture | The project department and some pictures of the Lanzhou New District of China Construction 3 are derived from the Internet

Edit | von Yifu

- END -

Walking in front of the new bureau 丨 Rizhao: More industrial integration stories are wonderful

On July 12, the newly developed pure electric vehicle Euler Ballet cat in Great Wa...

Entering the campus must scan the yard code

On July 12, the Municipal Education Bureau's Education System Education System Extraction Prevention and Control Work Conference required that education management departments and schools at all level...