Yibin: Strictly guard against the "protective network" of power supply to the power battery conference

Author:New Sanjiang Weekly Time:2022.07.20

On July 19, the power distribution and inspection class of the Sanjiang Power Supply Center of the State Grid Yibin Power Supply Center was carefully operated at the next batch of Hewanyuan electric vehicle charging stations in the next batch of Hewanyuan electric vehicle charging stations. The World Power Battery Conference convenes an atmosphere of application scenarios.

The 2022 World Power Battery Conference will be held in Yibin City from July 21st to 23rd. It is invited to attend important guests in politics, production, learning, research, research, merit, media, and media. The 25 important places and 14 ecological experience inspection activities and the power guarantee.

In order to do a good job of power supply to the conference, the State Grid Yibin Power Supply Company resolutely carrying political responsibilities, strictly implemented the electricity conservation plan. Citizens shared the green power feast.

image.png

"One case, one case" precision control emergency grid

"The conference specifications are high, the range of electricity is wide and difficult. Due to the particularity of the electricity conservation point, a electricity preservation solution and emergency plan are" customized "for each electricity guarantee point to ensure that when encountering an emergency situation It is not chaotic to ensure accurate and timely repair work. "Said Wang Hao, deputy director of the marketing department of the State Grid Yibin Power Supply Company.

In order to ensure the plan, measures, and responsibilities, the company has established a leadership group and five professional working groups with the general manager as the leader. The investigation of hidden dangers of changing equipment, customer -side electricity safety hazards investigation, emergency electricity preservation plan preparation, etc. to refine the requirements of "eight major points" 28 electricity preservation measures, and to strengthen the special patrol and hidden danger investigation and management of power distribution equipment to ensure the realization of "equipment equipment Zero failure, customer zero flash, work zero error "target.

"During the exercise, we conducted a special patrol of the external lines involved in the guarantee, conducted a temperature test of the ring cabinet, and inspected some electric equipment measured by customers to ensure that our equipment lines were stable, safe, and reliable. . "Hou Jianfeng, director of the marketing of the Sanjiang Power Supply Center of the State Grid Yibin, introduced.

In order to ensure the implementation of the measures and measures, on July 6, at the convention center of the convention and exhibition center, the State Grid Yibin Power Supply Company carried out actual combat drills, and the electricity consumption center, convention and exhibition center, Hengxu Hotel and other sites of Sanjiang New District were used. The issue is investigated one by one, sorted out the results, summarized uniformly, and urged users to make rectification.

At the same time, the company actively contacted the access and joint adjustment of the UPS power equipment and emergency trams of the International Convention and Exhibition Center, and guided customers to carry out full load tests to ensure that the power supply of important activities such as the opening ceremony of the conference and the main forum.

image.png

"One point and one strategy" to ensure the power supply of characteristic attractions in a timely manner

In the park with a strong bamboo culture, the green bamboo dances in the wind. Under the bamboo forest, the rows of LED lights are distributed, and the stars are bright. On July 15th, the 12,000 lamps installed in Bamboo Culture Park will be unveiled collectively to illuminate the bamboo culture park.

In order to do a good job in the power supply guarantee of the Bamboo Culture Visits of the Power Battery Conference, in March of this year, the Bamboo Cultural Park Light Lighting Promotion Project was launched in March of this year. Due to the wide range of power supply sources, there is no special power supply line, which adds a lot of difficulty to construction. State Grid Yibin Sanjiang Power Supply Center has repeatedly surveyed on -site, and comprehensively considers the problems of the transformer capacity and load distribution in the Taiwan area, the direction of the line, and the electrical fire and other hidden dangers. The work of the file and recording system is selected for the new installation power supply point, and actively overcome the difficulties of tasks and tight time. On July 8th, they were installed in electrical equipment.

In order to ensure the successful completion of the project, the power supply personnel adopted a continuous combat method, facing 40 degrees of high temperature weather, rushing the work period, grabbing time, and promoting the construction of the project. On the morning of July 12, the construction staff was pouring the power ring network cabinet. The electrical appliances not far away have been installed, and the power supply personnel are conducting the power facilities in an orderly manner.

"In order to effectively ensure the power supply of the project, we have built 9 new transformers in Zhu Cultural Park, with a total of 9,000 kilowatts of electricity load, 1 new ring network cabinet, more than 4,400 new cables, red purple, blue, yellow, yellow, yellow, yellow, yellow, yellow, yellow, yellow, yellow The light source becomes a rotation, and it is very shocking like the painting of splashing ink. "Said Shi Jian, director of the Marketing Department of Sanjiang Branch.

At present, the center will do a good job of communication and docking in other construction projects with the functional departments and project construction units of the Sanjiang New District Government. In accordance with the requirements prescribed by the superior, the construction progress of various power supply distribution facilities is promoted in an orderly manner.

image.png

"One Team, One System" fights on the spot to keep electricity guards

In order to give full play to the pioneering role of party members' assault teams, the State Grid Yibin Power Supply Company established a party building work integration mechanism for "unified command, resource collection, task collaboration, responsibility linkage, and joint construction". The team, divide 30 party members' responsibility areas, go all out to do the "four guarantees" targets that guarantee safety, power supply, power supply, service, and guarantee.

Since early July, the company has strictly implemented leadership leaders and 24 -hour duty systems. Pay close attention to the operation of various grids and emergencies, and make comprehensive preparations. Strengthen the operation analysis and risk prevention and control of the power grid, and do a good job of load prediction and electricity balance according to the weather conditions. Give full play to the advantages of the Communist Party member service team and party members' assault teams, and always prepare to fight on the field guards.

The party members' assault team carried out three rounds of electrical line equipment hidden dangers in advance to investigate and eliminate the shortcomings. The full -testing of the important load on the customer's side, the full test of the on -site equipment, the full test of the investment and cutting equipment, and the full test of the emergency power supply to realize the "zero perception" of power switching. During the meeting, the State Grid Yibin Power Supply Company will also send 160 employees to the 26 hotel -side power distribution stations involved in the meeting to implement the "customer party personnel+power supply party personnel+manufacturer support personnel" joint point. Together. Implement the customer -side electricity personnel to master the "one household and one volume" plan, encrypted equipment inspections and infrared temperature frequency, and eliminate hidden dangers of defects as soon as possible. At the same time, high -quality services are done for highlighting key areas and key objects to ensure that there is no negative impact.

Establishing more than 280 emergency emergency rescue rescue teams in accordance with the nearest configuration of the front -line team, supporting the team to gather the "dual insurance" method to ensure the rapid disposal of various types of equipment, and provide strong political guarantee for the successful completion of the power supply guarantee task of the conference. (Wang Qingqing, Chen Ling)

Information source: State Grid Yibin Power Supply Company

- END -

excellent!Quanzhou individuals and collectives on the list

Recently, the Quanzhou Municipal Party Committee of the Communist Youth League, Qu...

Sanfu poison is hot day, it is recommended to eat more "bitter dishes", refreshing and greasy, comprehensive nutrition, comfortable summer summer

After entering the midsummer, I finally felt the coming of the hot summer. When I ...