The wall of the Chengdu Longdu International Community cracks?Longquan Resident Construction: Design unit is formulating a rectification plan

Author:Cover news Time:2022.07.19

Recently, some netizens complained about the quality of Longdu International projects through the Sichuan Daily's "Ask Guanzheng Sichuan" platform, saying that 8 buildings and 1 units entering the elevator mouth negatively, and the walls were found. Netizens said that they did not know if the foundation was sinking, and worried that the stairs would cause related issues such as the collapse of the stairs.

On July 19, the Housing and Urban -Rural Development Bureau of Longquanyi District replied: confirmed that there were cracks and damage in the basement wall, and the problem of cracking and water in the basement of the basement and the side wall.

A total of 2470 households in the community

The unit price of hardcover in 2018 is about 9,000 yuan/㎡

"There are a lot of problems before handing over the house. Now there are problems with the elevator every day." According to netizens, many problems currently existing in Longdu International have not been resolved. For example, at the beginning of the elevator's mouth at the negative layer of the 8 units and 1 unit, the walls were found. The owners were worried that the phenomenon was caused by the foundation of the ground, and even worried that the stairs would collapse. In the end, the netizen called for "the relevant unit to pay attention to it."

From the live photos provided by the owner, it can be seen that the basement of the community has appeared very obvious cracks, and the wall tiles are exposed.

Public information shows that Longdu International is located at No. 399 Longdu North Road, Longquan District, Chengdu. The project covers an area of ​​94 acres and the construction area is 360,000 square meters. The developer is Chengdu Chenggongka Real Estate Development Co., Ltd. The project is developed in three phases, with an apartment area of ​​75-135 square meters, with a total of 2470 households. At present, the house has been sold out. In April 2018, the second -stage opening of hardcover costs was about 9,000 yuan/㎡.

Longquan residence construction:

Confirm that there are problems such as cracking and water seepage

The design unit is formulating a rectification plan

Regarding the issue of complaints from netizens, on July 19, the Housing and Urban -Rural Development Bureau of Longquan District replied that netizens reported that the wall of the Longquan District Longdu International 8 Building 8 of Longdu District was cracking. The staff of the quality supervision station organized the construction, construction, and supervision units on June 30, 2022 to conduct on -site explorations to confirm that there was a cracking and destruction of the basement wall of the basement. On June 30, 2022, the quality supervision station interviewed the construction, construction, and supervision units, and requested the construction unit to organize the problem of on -site survey of the problem of water seepage and filling the wall of the basement, designing, construction, and supervision units. , Formulate a special treatment plan and deal with regulations. On July 4, 2022, the construction unit organized the problem of on -site survey on the problem of water seepage and cracking of the basement and the cracking and damage of the filling wall, analyzing the cause, and formulating a special treatment plan. At present, the design unit is formulating a rectification plan. Regarding the problem of returning to the tidal wall of 9 units and 202 units, the staff of the quality supervision station has instructed the construction unit to investigate quality issues, earnestly fulfill the quality warranty obligations, and rectify according to regulations.

The reporter's inspection found that on May 11, 2021, some netizens complained that the extension of the house in the second phase of the Longdu International Community, the unlicensed house, the poor quality of the house, the exterior wall tiles dropped the drum bag, the lobby ceiling leakage, the severe alkali return, and the floor depression.

On May 25, 2021, the official response stated that the person in charge of the development enterprise of the Market Science and Construction Bureau of Longquan District Housing and Urban -Rural Development Bureau immediately issued the "Notice of Ordering Time to Rectification" and ordered the development enterprise to stop the delivery activity immediately. Delivery; parts of the project have water leakage, the wall of the wall, and the floor depression of the floor. The situation is true.

Cover news reporter Huang Yihui

- END -

(Release of rights) List of the Standing Committee of the National People's Congress decided to appoint and remove

Xinhua News Agency, Beijing, June 24th.The list of standing and removal of the Standing Committee of the National People's Congress decided(The 35th meeting of the Standing Committee of the 13th Natio...

The heavy rain struck the city, the Foshan Iron Police supported you "Ping An Umbrella"

Recently, heavy rainfall in western Guangdong and Guangdong, and a large -scale co...