In 680 days, a large stadium was set up in flat ground
Author:Rizhao News Network Time:2022.08.26
In 680 days, a stadium with a total construction area of 143,000 square meters -Rizhao Kuishan Sports Center "Rizhao Light" stadium rose up, ending the history of Rizhao without large stadiums. Such a large amount of engineering takes 3 years to complete.
"The opening ceremony is there, there are no conditions to talk about, only dry, dry, and dry." Said Lu Haitao, manager of the Urban Development and Construction Company of the Rizhao Economic Development Zone Economic Development Group. After the project was started, under the premise of ensuring construction quality and construction safety, it was a satisfactory answer sheet to fight against time, fighting day and night.
Grab the time: one table, one table, one strategy, push the project to accelerate the catch
Rizhao Kuishan Sports Center started in December 2019. In early 2020, the epidemic of new crown pneumonia was suddenly.
"It would be a hurry to die." Zhang Changcheng, manager at the project site, recalled. The engineering construction unit is the eight bureaus of China Construction, and most of the construction workers are foreigners. During the prevention and control of the epidemic, people and cities from other provinces could not enter. Insufficient, the construction period was delayed for 3 months.
The District Economic Fa Group divides the entire project into more than 300 nodes, and formulates a detailed construction operating plan for each important node project. All venues, one -time one, one strategy, and hanging chart promotion. Weekly meetings, monthly regular meetings, quarterly regular meetings, progress analysis meetings, and annual summary meetings.
Every day, the person in charge of the project is soaked in the project, organizing design, supervision, and construction units to optimize the construction process and save time; the process by item, one node analysis, and interspersed the construction time in advance.
"At most, there are more than 1,200 people and more than 1,000 machinery on the construction site. The scene is really spectacular." Zhang Changcheng joked. Finally, in the spring of 2021, the delayed construction period was chased back. The "Light of Rizhao" stadium was approved in April this year.
1 floor underground, 4 floors above the ground, 680 days, a 42 -meter -high, 273 meters north -south, and a span of east -west span of 242 meters.
Grab quality: standardize standards, strict construction, and build high -level stadiums
The 25th Provincial Games is the first Provincial Games after Shandong started the new journey of sports in the new era. It is also the first high -standard, large -scale, high -competitive comprehensive sports event organized by Rizhao City. , Everyone's attention.
Prior to this, Rizhao Economic Development Zone and even Rizhao City did not have the experience of building large stadiums. Rizhao Kui Mountain Sports Center was the main venue of the Provincial Games. There are many, professional, and unprecedented pressure.
How difficult is it?
"Just take the steel structure, the maximum span of the steel structure of the stadium is nearly 40 meters, especially the roof steel truss is ring -shaped, with complex forms, high process requirements, and difficulty in processing." The amount of steel for the entire stadium is more than 3,000 tons, and it is very difficult to hang high altitude. We used 1250 tons of crawler cranes at that time. There are few in China. The roof adopts the international leading film structure and has high requirements for the construction process. "
Without experience, the Group hired a professional sports craft consultant company to help plan in the early stage. After the construction starts, it will conduct regular on -site guidance, and encounters difficult problems to contact professionals for treatment as soon as possible; formulate a special construction plan, standardize standards, and strictly build the plan.
The track and field venue is a dual -standard venue that meets the international and domestic single track and field events. It requires high requirements for the flatness and slope of the venue. The radius of the venue is 36 meters. Error requirements.
"The quality of this track is much better than the track we usually train, and it is very comfortable to run."
"The game venue is particularly good and the auxiliary facilities are fully prepared."
Several tests and competitions have proved that the venue of the sports center has been tested.
Strong operation: work together, work hard, and dedicate wonderful provincial games
On May 11th, the "Rizhao Light" stadium ushered in track and field test competitions, rugby competitions and other events, and the stadium was transferred to the operation and maintenance stage.
Rizhao Kuishan Sports Center will undertake the opening ceremony of the 25th Provincial Games, track and field, skateboarding, rugby and other competitions. It is a top priority to ensure that the opening ceremony and various events are going smoothly.
The district Economic Fa Group formed the operating work of the Rizhao Kuishan Sports Center. From the aspects of venue guarantee, equipment and facilities, and epidemic prevention and control, it is fully escorted.
There are 36,000 seats in the stadium. These seats are wiped all over again, and hundreds of people can be wiped for two or three days!
No one shouted hard and tired, everyone worked together to contribute to the Provincial Games.
On the afternoon of June 26, the 25th Provincial Games Rugby Competition Men's Group A Group Finals started. At 16 o'clock, the heavy rain was pouring, but the game was ongoing.
Within 20 minutes, complete the grass shop stickers!
After asking the referee, the special class was separated. Some of them were supplemented with grass skin, some were sandwiched, and some were looking for flat. In less than 20 minutes, hundreds of pits were filled, and the game returned to normal.
"You must top it at the critical moment!"
The opening ceremony of the drone shows that the light base needs to be installed. In less than 2 months, it is built day and night, and 572 lighting bases have been installed. The rough rooms rented out to the outside world need to be temporarily changed to a dressing room and lounge. In less than a month, water, electricity, simple decoration, more than 30 rooms have been changed.
At most, there are 24 games a day. The event guarantee and hygienic cleanup, from 5 am to 89 pm.
During the skateboarding competition, the summer heat was hot. Huoxiang Zhengqi water became the standard for each service staff. Drink a bottle before playing, and some personnel have arranged the top of the people at any time.
This has not been considered countless debugging and rectifications of the equipment facilities and lighting audio. "Although it is tiring and there is no experience in serving large -scale games, everyone takes this experience as an opportunity for self -experience and improve themselves." Said Zhou Wenzheng, the person in charge of the operating work class of Rizhao Kuishan Sports Center.
With first -class venues, first -class services, first -class environments, build a stage for showing gels and chasing dreams for sports athletes in the province, and dedicate a wonderful and unforgettable sports feast for the people of the province. Intersection (Reporter Mu Yanxia Correspondent Han Xing Bo Lin)
- END -
World Football Turn this summer, the list is released: Barcelona's 153 million ranked first!Premier League three teams enter the top five
The list of transfer expenditures this summer: Barcelona ranks in the top two, and...
The first National Women's Ice Hockey City Invitational Tournament started in Harbin
On July 14, China Harbin's first National Women's Ice Hockey Cities Invitational T...