Wuhan's autumn school will ensure that 65 kindergartens in primary and secondary schools are delivered and used, adding 40,000 degrees

Author:Pole news Time:2022.08.11

Jimu Journalist Guoqian

Correspondent Zou Yongning

On August 11, Jimu Journalists learned that in the fall of this fall, Wuhan City will ensure that 65 primary and secondary school kindergartens are delivered and used, adding 40,000 degrees.

On August 10, Li Chao, Secretary of the Party Committee of Wuhan Education Bureau, and his party investigated the promotion of major project construction in Hongshan District to ensure the supply of autumn degrees. At 4 pm, Li Chao and his party successively went to the sixth elementary school in Hongshan District and the Hongshan District Experimental Kindergarten Project Department to learn about the promotion of the construction of major education projects, and held a meeting to solve the problem of "urgency and sorrow" of the current education line. Xiong Guanghua, Secretary of the Party Committee and Director of the Hongshan District Education Bureau, introduced that this year, the number of freshmen in Hongshan District primary and secondary schools has reached 15,000. As of now, 11 schools have been put into use, including 9 new schools, 2 expansion schools, and 9 schools During the construction, the needs of residents in the jurisdiction will effectively meet the needs of residents in the jurisdiction.

Li Chao, Secretary of the Party Committee of the Wuhan Education Bureau, and his party investigated in the sixth elementary school in Hongshan District (the picture was provided by the correspondent)

Wang Jifang, director of the Development Planning Division of the Wuhan Education Bureau, introduced that in 2022, Wuhan City was included in major educational projects in the municipal government's actual affairs and the performance goals of various district governments, with a total of 266 categories. These include: 84 new and expansion projects in public kindergartens, 150 primary and secondary schools with construction projects, and 32 school running conditions construction projects in high schools. Through the planning and overall planning of the government, party members and cadres "lower grassroots, inspect the people's sentiment, relieve the people's concerns, and warm the people's hearts" practice activities, the Wuhan Education Bureau promotes the implementation of the project in place.

As of now, 84 new and expansion projects in public kindergartens have completed 226 million yuan, accounting for 72.9%of the planned investment; 70 have started (including completion), with an operating rate of 83%. Among them: 38 were completed, 32 were started in construction, and 14 were in the pre -construction procedures for construction bidding.

150 primary and secondary schools have completed investment of 3.7 billion yuan, accounting for 92.5%of the planned investment; 79 have started (including completion), with a startup rate of 52.7%. Among them: 22 projects have been completed, the main structure of the 19 projects is completed, 17 subjects are constructed, 21 new startups are started, and the rest of the construction is procedures for construction.

32 construction projects for school running schools in high schools have completed 702 million yuan, accounting for 79.1%of the planned investment; 22 have started (including completion), with an operating rate of 68.8%. Among them, six completed, 5 main structures were completed, 4 of the 4 subjects were constructed, 7 new construction construction, and the rest were in the pre -construction procedures.

It is understood that in order to supervise the completion of these projects, the Wuhan Education Bureau has issued an annual construction plan in advance and determined various performance goals; the city's promotion deployment meeting and establishing a promotion mechanism are held; pre -allocated annual city -level project funds to ensure project progress.

"We have previously issued a 2022 construction plan for kindergartens, primary and secondary schools, and high school. Among them, the construction project of primary and secondary schools is jointly issued by 4 departments including municipal education, development and reform, finance, natural resources and planning. The Organization Department listed the 2022 kindergarten and primary and secondary school construction projects as the performance goals of various district governments. Kindergartens and primary and secondary school construction work in the parks and enrollment contradictions were included in the assessment of the annual performance goals of various district governments to further implement the government of various district governments. Effectively fulfill the main responsibility of basic education management. "The relevant person in charge of the Wuhan Education Bureau introduced that on April 22 this year, it also organized a video meeting for the construction of major education project construction in 2022, which conducted a comprehensive deployment and exchanged advanced typical projects. The unit promotes experience and puts forward clear target tasks.

At the same time, information technology is used to promote the supervision mechanism of weekly scheduling, monthly reminder, quarterly notification, quarterly notes, leading offices "weekly running", and bureau leaders "key running". In early July, a city dispatch meeting was held to issue the "Working Tips for the Promotion of the Municipal Education Bureau on the Promotion of the Promotion of the Municipal Education's Major Education Project in January to June" in various districts. "In early 2022, we have allocated annual city -level project funds to the district. At the same time, we requested to support the corresponding funds of various district governments to use channels such as government special bonds to ensure that the project is constructed as scheduled." The person in charge said.

In the next step, the Wuhan Education Bureau will strengthen supervision and increase overall coordination. The leaders of the bureau led the "difficulty" project, supervised on -site, increased coordination, and emphasized that under the premise of ensuring the quality of the project, epidemic prevention safety and construction safety, the project construction progress was accelerated. And it will be accelerated to ensure that the autumn degree supply is in place. Pay close attention to the various goals of the year, seize the golden time of the summer school, speed up the advancement, and ensure that it is completed as soon as possible in the autumn projects and the degree supply. Effectively solve the problem of "difficulty in entering the park and difficulty" in local areas.

- END -

Recruit 6,000!Fresh university graduates come here

Recently, the joint education department, the Provincial SASAC, the Department of Finance and the Human Resources Department of the Science and Technology Department jointly issued the Implementation

Linyi High School Entrance Examination started today!These reminders, please pay attention to candidates and parents

After the college entrance examination was successful, the middle school entrance ...