Repairing the old as the old, the Arrow buckle the Great Wall repair and explore new path

Author:Report Time:2022.08.22

undefined

Limited by the environment, workers use livestock materials to go up the mountain (taken on August 16).

At the end of it, the construction of the two repair sections of the Great Wall on the northern suburbs of Beijing was under construction. The "West Wall" on the west side of the Arrow Capital Great Wall is the place where the fourth renovation project of the Great Wall of the Great Wall is located. There are 8 enemy platforms on the wall with a length of 1678 meters. The renovation project in the fourth phase will be completed at the end of October, and the project has been completed about 70%.

Great Wall repair still adheres to the principle of "minimum intervention, repairing the old as the old", try to use old bricks and follow the ancient method. On the premise of ensuring the safety of the Great Wall's body, the "old" of the Great Wall has been retained. Mature experience.

The "Western Wall" on the southeast, about 486 meters long (141 to 145 enemy platforms) is undergoing a "research repair". Different from general repair projects, research repair must not only discharge and reinforce, but also cooperate with multi -disciplinary cooperation through archeology, construction, materials, construction technology, plants and other disciplines to study the evolution process of the Great Wall ontology, the cause of the disease, and the environment. At the scene, Shang Yan, an associate researcher at the Beijing Archaeological Research Institute, pointed at a collapsed wall of the enemy platform on No. 145 and said: "The disability is part of the culture of the Great Wall ancient heritage. More people understand the root causes and collapse of the wall. "

Since 2021, Beijing has shifted the focus of Great Wall protection work from the general protection project of the Great Wall to a research repair project. This is a new exploration of the Great Wall protection and repair. Through preliminary archeology, the research repair of the Great Wall of Arrows has been excavated at 145, 144, and 143. Cultural security personnel clarified the architectural shape and engineering practices of the enemy platform. For the first time, they found the relics of the Ming Dynasty fire, stove address and other living facilities inside the enemy desk. The subsequent repair plan provides a design basis.

The Great Wall Repair Project is a key project for the construction of the Great Wall National Cultural Park (Beijing Section). At present, the Great Wall of about 10 kilometers has been completed and repaired by 5 kilometers. With the consent of the State Administration of Cultural Relics, the nation's first Great Wall Protection and Repair Practice Base was established at the foot of the Great Wall of the Arrow Capital in September 2020, which has played a demonstration effect on the national Great Wall protection work.

undefined

The famous landscape of the Great Wall "Beijing knot" and the "Western Wall" section of the northern part of the northern part (photo taken on August 16, drone photos).

undefined

Engineer Cheng Yongmao was walking on the "Western Wall" section. The ground under his feet is reinforced and repaired according to the original structure and residual characteristics to ensure the safety of pedestrians, and at the same time, it also retains some vegetation that does not threaten the wall (taken on August 16).

undefined

Workers collected mountains and stones in the "Western Wall" section for repair stones, and follow the ancient "local materials" to repair the Great Wall (taken on August 16).

undefined

Workers are constructed in the "Western Wall" section (taken on August 16).

undefined

Workers are constructed in the "Western Wall" section (taken on August 16).

undefined

Engineer Cheng Yongmao inspected the enemy platform 158 in the "Western Wall" section. After repairing the old bricks, the coupon hole in the enemy Taiwan restored the old appearance (taken on August 16).

undefined

Workers' archeological sites in the research repair section (taken on August 17).

undefined

Workers retained the root of the tree in the process of research on archeological excavations to further study the Great Wall plant disease (taken on August 17).

undefined

Arrow buckle Great Wall Research Repair Section 144-141 (Photo on August 17, Photos of UAV).

undefined

The fourth phase of the Great Wall Repair Project "West Wall" section (taken on August 16).

undefined

This is an archaeological point on duty all day in the research repair section.

undefined

The technician Yang Zhanjie (right) guided the workers to set the scope of research and archeological excavations (taken on August 17).

undefined

At the construction site of the "West Wall" section, the workers transported the construction materials under the wall to the Great Wall through the mechanical pulley (taken on August 16).

undefined

This is a photo -spelling photo: the picture above shows archeological excavations in a site in the research repair section; below is the workers cleaned the ground and collected some relatively complete old bricks for subsequent follow -up work after some excavation work. Repair (taken on August 17).

undefined

Workers engaged in research on the construction site were on their way to the construction site and passed on the 142 enemy Taiwan (taken on August 17).

undefined

This is a picture of several enemy desks on the research repair section: the top left is No. 142 enemy platforms that are under archeological excavations; the top right is No. 143 enemy platforms that have been completed in archeology; No. 145, which has been excavated in archeology (taken on August 17, drone photos).

undefined

Workers conducted archeological excavations on the wall near the enemy platform No. 145 of the research repair section (taken on August 17, drone photos).

undefined

The technician Yang Zhanjie put the reminder note on the wall of the enemy platform No. 143 on the research repair section 143 (taken on August 17).

undefined

After the workers have completed the archeological excavation, the No. 144 enemy Taiwan went to a research renovation site (taken on August 17).

undefined

Workers conduct archeological excavations at a research site (taken on August 17).

undefined

Workers conduct archeological excavations at a research site (taken on August 17).

undefined

This is the Ming Dynasty fire and stove site excavated on the enemy platform No. 145 (taken on August 17).

undefined

Shang Yan (second from left), an associate researcher at the Beijing Archaeological Research Institute, introduced to the media reporter.Engineer Cheng Yongmao was on the way to the "Western Wall" renovation site (taken on August 16).

undefined

In the early morning of August 17, Yang Zhanjie (left), technicians engaged in research repair, and workers resting on the mountain road on the Great Wall.

undefined

Workers conduct archeological excavations at the research site (taken on August 17).

undefined

This is No. 141 (front) of the 141 enemy Taiwan (front) that is about to enter the research repairs, No. 142 (middle), which is under archaeological excavation, and No. 143 enemy Taiwan (later) that has been completed in archeological excavation (taken on August 17, drone photos)Essence

undefined

Edit: Chen Chen

Editor in charge: Wang Wei

Source: Xinhuanet

- END -

Love is too easy, letting love is the most difficult part

One poem and one article every day's original poems and dreams, don’t pass by wit...

Shenzhen "New Era 10+2 cultural facilities" gradually started construction

Under the Pingshan River and under the Yanziling, the pile foundation is promoted ...