Caramay: 160 trucks have been unloaded one after another to promote the construction of new energy projects

Author:Tianshan.com Time:2022.08.29

Tianshan News (Reporter Guan Xiangrong, a correspondent Guan Xiangrong, Correspondent Guan Xiangrong) On August 29, a truck with a full -load component, bracket, and box change of new energy materials drove into Krama Yi's New Energy Co., Ltd. The construction site of the 50 MW photovoltaic power generation project of Energy Caramay was unloaded smoothly.

The "50 MW photovoltaic power generation project in Karamay District" is currently in the stage of equipment installation and debugging. Guan Xiangrong confession map

"At present, the construction period of our new energy project is relatively tight. In the past half month, 160 trucks have entered the project site one after another. Today, 13 vehicles were unloaded smoothly today, allowing our construction period to advance normally." Zhang Xiaoping, the project manager of Energy Co., Ltd., said.

It is reported that the total investment of Clarma Yihui New Energy Co., Ltd.'s "50 MW photovoltaic power generation project" of the "National Comprehensive Energy Caramay District" was built at the end of November 2021. The project is currently in equipment installation and debugging, and the grid -to -network procedures are processed. It is expected to be completed and put into operation by the end of September this year.

At that time, the project can generate 80 million kilowatt -hours of electricity each year, helping Karamay to build a new type of power system and create a "depression" of electricity prices.

In order to ensure that the project is completed on time during the construction period, the Karamay Development and Reform Commission jointly combined and deploy human resources with relevant functional departments. In response to the shortage of manpower in the enterprise, they planned with the relevant departments in advance, and arranged special vehicles to pick up and drop off the relevant staff. At the same time, it helps enterprises to unblock cargo transportation channels.

The trucks full of new energy materials enter the project site in an orderly manner. Guan Xiangrong confession map

"For the supply of components and brackets, the Karamay Municipal Development and Reform Commission communicates with relevant departments in time to apply for key material transportation passes for new energy companies to ensure that components, brackets, and box changes can be present in time." Director Zhang Jianjun said that after the new energy project construction enterprises put forward the demand, the relevant functional departments will lead the team to bring the vehicle to the project site, and the truck will be unloaded as soon as possible.

- END -

Deep Reading | Heshan Juli China -Europe Cooperation Spring Top "Top 100"

Juli Juli cooperation between Heshan City. On July 30, Jiangmen North Station issu...

Get first!Grasp the project and expand the investment in Qiantang to promote the stable and healthy development of the economy

Grasping major projects, expanding effective investment is an important starting p...