The construction of the project of the coal reserve base of Western Henan Henan Henan Henan is in full swing
Author:Henan Daily Client Time:2022.08.25
Henan Daily client reporter Wang Xiaoping Wang Xuehong correspondent Dong Yinghui Zhang Yitao
On August 22, the construction site of the project construction site of Western Henan Coal Reserve Base in Henan, with a length of 651 meters, a span of 120 meters, and a height of 42 meters, the main structure of the mesh shelf of the coal shed "The homework is like a" Spider -Man ", and it is installed at a high altitude of tens of meters.
Liu Jizhe, deputy director of the project preparation department, introduced that during the construction of the main body of the coal shed, the project team overcame the real problems such as the complex geological conditions, the high -level high -level operation of the arched structure, the difficulty of high -altitude operations, and the high temperature. The method of "steel bones" is weaved for this large steel structure coal shed. Starting on June 16th, more than 200 workers successively followed up and night, operating 45 pile machines, 35 engineering vehicles, 4 50 -ton crane machinery, in just over two months, all processes such as assembly and lifting were completed in an orderly manner. Weaving "steel dome".
"The total construction area of the project is about 81875 square meters, and the total steel volume of the project reaches more than 4,700 tons. In order to ensure that the project is implemented in accordance with the progress, the Yima Municipal Party Committee and Municipal Government closely track the monitoring and solve the problems of the project construction. Study to solve major difficulties in restricting the project promotion, and ensure the smooth progress of the project. "Liu Jizhe said.
Henan's western Henan Coal Reserve Base Project is one of the eight major reserve coal bases in the country. It is one of Henan's largest coal reserve centers and one of the "three batches" activities of the second phase of Henan Province. It has been included in major national construction projects The development plan of the "14th Five -Year Plan" of Henan Province, the key project of the province in 2021.
The main function of this project is the national coal strategic reserve, with a total scale of 40 million tons/year (static reserve capacity of 3 million tons) and a total investment of 3.945 billion yuan. The overall planning and staging implementation of the project is divided into recent and long -term construction. The recent implementation scale is 20 million tons/year (the static reserve capacity is 1.21 million tons), and the investment is 1.96 billion yuan. It is mainly composed of coal reserves and railway special line projects, including Changcun reserve area and Beilu Tianbei reserve area. Among them, Changcun reserves The size of the area is 5 million tons/year, and it has been completed and operated; the size of the reserve area on the north side of Beilu Tian is 15 million tons/year. It is a new project and plans to invest 360 million yuan. The long -term project is located in the reserve area on the south side of the Beilu Tian. The construction scale is 20 million tons/year (the static reserve capacity is 1.79 million tons), and the estimated investment is 1.985 billion yuan.
- END -